Is there a "standard" way of bolting racks down that is interchangeable between vendors?
At our datacenter we've standardized on a Damac rack for our builds. Because we're building in volume, the colo provider works ahead to bold down our racks (raised floor, all-thread into concrete below and anchored to the floor tiles as well). This is in zone 4 earthquake area.
We've auditioned a competing rack from Rittal and found that it doesn't attach to the pre-drilled holes w/o a custom bracket.
Is there a standard for holes to bolt racks down or does everyone do it their own slightly different way?