My backup system is currently shut down do the library being broken. I am going to attempt to repair the library, but want to make sure none of the current data that is past the retention period gets over written. Is there a simple way that I can start netbackup, but put a halt on any back processes before they start?

share|improve this question
    
I did cancel all jobs from the GUI, but wondering if there something I can do make sure no more start. I Don't think any of the policy's have an open window right now, but wondering what additional lock I can do other than the physical switch on the tapes. –  Kyle Brandt Apr 6 '10 at 12:39

1 Answer 1

up vote 2 down vote accepted

Scheduled jobs can be prevented with:

bin\admincmd\nbpemreq -suspend_scheduling

bin\admincmd\nbpemreq -resume_scheduling
share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.