I'm using Windows Server Backup on 2008 server. Is it possible to have multiple backup jobs from within that program? I would like to schedule a full backup on Friday and an incremental backup the Monday - Thursday. Is this possible using WSB?

share|improve this question
add comment

1 Answer

Yes, using the command line/scheduled tasks. Not sure about using the GUI (I don't use it, myself, command line is easier to make sure it is consistent/what you expected).

Reference: http -> blogs.technet.com/b/filecab/archive/2009/04/13/customizing-windows-server-backup-schedule.aspx