I have two ESXi 5.1 hosts booting from USB sticks. One host is the production server the second is for testing. I would like to make some configuration changes in the test box, make sure they work and then move them to production. The test host is an old AMD box and production is a brand new Intel machine. Needless to say they are completely different hardware in every respect, except they both boot from a USB stick and they both run the same free version of ESXi 5.1.

What is the best way to move the tested configuration changes to production?

share|improve this question
2  
Implement them and then test them on the test box then implement them and test them on the production box. Why you would want to "migrate" them is a mystery. –  joeqwerty Feb 28 '13 at 18:55
    
What type of configuration changes? –  ewwhite Feb 28 '13 at 19:05
add comment

1 Answer 1

up vote 2 down vote accepted

You could just move the USB drive. But much of that depends on what type of config changes you were making.

The better approach would be to keep track of your configuration changes and apply them to the destination system.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.