Is there a "standard" way of bolting racks down that is interchangeable between vendors?

At our datacenter we've standardized on a Damac rack for our builds. Because we're building in volume, the colo provider works ahead to bold down our racks (raised floor, all-thread into concrete below and anchored to the floor tiles as well). This is in zone 4 earthquake area.

We've auditioned a competing rack from Rittal and found that it doesn't attach to the pre-drilled holes w/o a custom bracket.

Is there a standard for holes to bolt racks down or does everyone do it their own slightly different way?

share|improve this question
    
A bit naïve but perhaps adding a short deck between the floor and the cabinets to allow free adaption to any cabinet would be of benefit. I would guess that raised floor systems and typical datacenter design guidelines make that a bit more prohibitive –  JustinC May 30 '13 at 5:37
add comment

1 Answer

up vote 11 down vote accepted

Sadly every rack provider is different depending on how they are assembled. If you switch you'll be either be replacing floor tiles or you'll have extra holes in the floor which need to be covered/plugged.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.