Folks, Is hardware sizing and capacity planning same? I have seen these terms being used together and google does not return any results that help me understand the difference.
Would appreciate any explanations.
regards, avajurug
|
Folks, Is hardware sizing and capacity planning same? I have seen these terms being used together and google does not return any results that help me understand the difference. Would appreciate any explanations. regards, avajurug | |||
|
feedback
|
This question came from our site for professional and enthusiast programmers.
|
There is a very accurate difference as explained by Joel in Capacity Planning, H/W Sizing:
| |||
feedback
|
|
I would call hardware sizing the initial step. After you sized your hardware, you hope that it will be able to meet the demands for a period X. Capacity planing is rather an ongoing process, by which you make sure that the system will be able to meet the loads of the changing demands. You decide when you want to add more power to the enviroment (before or after the limits are reached) | |||||