I have a large number of scheduled tasks we've like to move off a Windows 2003 server to a new Windows 2008 server.

I have a couple of questions

  1. Can I just copy the .job files to the new server and reset the passwords?

  2. If this is not possible, is there a way to turn each .job file into a user readable format, or even better, reverse engineer to a command line statement or script?

share|improve this question
add comment

1 Answer

up vote 3 down vote accepted

Can I just copy the .job files to the new server and reset the passwords?

No. Basically, the job files under Windows 2003 and Windows 2008 are of different format (binary vs. XML-based)

If this is not possible, is there a way to turn each .job file into a user readable format, or even better, reverse engineer to a command line statement or script?

I know someone wrote a perl script to parse the binary data of Task Scheduler 1.0 job files into human-readable. Take a look here.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.